All utility work is now complete on Friday, April 24. Stormwater drainage pipe and roadway subbase - completed, as of Friday, May 8. Roadway and Bridge construction work in progress: installation of drainage inlets & castings, concrete curbing along concrete approach slabs, granite block curbing at approach roadway, riprap slope protection - in progress as of Monday, May 11.
Roadway paving is scheduled for Tuesday, May 12.
Remaining work before Pottersville Road can be reopened includes: sawcut groove concrete deck and concrete approach slabs, silane surface treatment concrete deck, beam guide rail and end terminals, traffic striping and regulatory signs.
Other remaining work to be done concurrent with roadway work and after Pottersville Road and Riverview Drive are reopened includes: completion of 4-bar bridge railing, stone veneer, concrete approach sidewalks, concrete waterproofing coating, final grading, topsoil & seeding, final clean-up.
We will continue with updates on the County’s website:
Road Projects/Construction Announcements | Somerset County
and the project-specific webpage: