9/14/2022 - 2022 Slurry Seal Pavement Preservation Construction Schedule- Asphalt Paving Systems

2022 Slurry Seal Pavement Preservation Construction Schedule- Asphalt Paving Systems


Please see the following notice for upcoming construction for the Slurry Seal Pavement Preservation with Asphalt Paving Systems. This work will be performed during the working hours of 8:00pm-5:30am with the road being opened to traffic each morning. The road will be closed to thru traffic and a detour in effect during the slurry seal operations only. Following the completion of this construction work, the final thermoplastic striping will take place approximately two weeks after construction. This schedule is subject to change due to inclement weather.

Slurry Seal Pavement Preservation Working Hours 8:00PM-5:30AM

Mon 9/19- Wed 9/21- CR647 Mendham Rd in Peapack Gladstone from County Line to CR512 Main Street, CR512 Pottersville Rd/Main St in Peapack Gladstone from Route 206 to 1,000' south of Ramapo Way, & CR671 Old Chester Road in Peapack Gladstone from Brookside Drive to Dewey Ave
Thur 9/22- CR525 Claremont Road in Bernardsville from Rt.202 to Mendham Rd
Fri- 9/23- CR640 Lyons Road in Bernards from Quincy Road to Stonehouse Rd
Mon 9/26- CR613 Stonehouse Road in Bernards from South Finley/Lyons Rd to Valley Rd
Tues 9/27- Wed 9/28- CR653 Stirling Road in Watchung from Verona Pl. to Watchung Circle & CR653 Stirling Road in Warren from County Line Bridge to Rt. 78 Bridge
Thur 9/29- Fri 9/30- CR533 Millstone River Rd/Main Street in Hillsborough/Millstone from Somerset Courthouse Road/Main Street to Blackwells Mills Road
Mon 10/3- Tues 10/4- CR601 Belle Meade Blawenburg Road in Montgomery from Grandview Road to CR518

Please click here for more information